A client cannot establish your agreement to new purchase-order terms merely by issuing a revised document. First identify which terms were accepted and then examine whether you agreed to a change, expressly or by conduct. Do not ignore the revision while continuing work as if the disagreement does not exist.
Section 7 of the Contract Act requires acceptance to be absolute and unqualified. Sections 8 and 9 recognise acceptance by performance and implied promises. Section 62 addresses an agreed alteration or substitution of the contract. Together, those provisions make the actual sequence important. The latest file date does not decide the bargain on its own.
Which document became the original contract?
Collect the quotation, original purchase order, acceptance, master agreement and attachments. Identify the offer and the exact response that accepted it. A quotation subject to later approval may not have the same effect as a signed order accepted without qualification. If your acceptance changed a material term, that needs examination too.
Read any order-of-precedence clause. It may state whether the master agreement, statement of work, purchase order or supplier terms controls a conflict. Do not assume that a purchase order automatically overrides a negotiated agreement. Equally, do not assume that a document called administrative cannot contain operative terms. The service-agreement drafting guide explains the value of identifying that hierarchy.
What changed in the revised purchase order?
Prepare a comparison identifying the actual differences. Price, delivery date, specifications, acceptance testing, payment period, indemnity, warranty and dispute resolution can all change risk. A correction to the billing address is different from a new clause transferring unlimited liability to you.
Preserve the original files and transmission records. Keep the message explaining the revision, not just the attachment. If the client says the change was discussed by telephone, make a truthful dated note identifying participants and what was said. Do not reconstruct a supposed agreement after the dispute has started.
| Record | Question it answers | Contract Act context |
|---|---|---|
| Original offer and acceptance | What bargain was concluded? | Sections 7-9 |
| Revised PO and covering message | What amendment was proposed? | Section 62 |
| Later emails and performance | Was the change accepted by words or conduct? | Sections 8-9 and 62 |
Can continuing performance amount to acceptance?
It can be material. If the client clearly proposes changed specifications and you manufacture and deliver to those specifications without qualification, the conduct may support an argument that you accepted them. That is different from completing goods already manufactured under the original order while expressly disputing an unrelated new risk clause.
The effect depends on the facts and contract. A general reservation in an email is not guaranteed to neutralise conduct that plainly accepts the proposal. Before proceeding, identify what you are willing to perform and on what basis. Ask for confirmation from the authorised contracting person rather than relying on a procurement portal's automatic status message.
What should I put in my response?
Identify the original PO and acceptance, list the disputed revisions and say which terms you accept or decline. Explain any price or schedule impact of the requested change. If you can continue the original work, state the basis clearly. If you cannot safely continue, obtain advice before suspending or missing delivery.
A response should also request a corrected PO or signed amendment reflecting the agreed outcome. Avoid merely writing that all rights are reserved while processing the revision internally as approved. Your sales, project and finance teams should understand which version is operative. Conflicting instructions within your company can create the very conduct dispute you are trying to avoid.
Identify each changed clause, the original wording, proposed wording, commercial effect and your response. Keep the comparison with the signed contract and the final accepted amendment rather than treating it as a substitute for agreement.
Who is authorised to agree to the change?
Check the contract's authorised-representative and amendment provisions alongside the people involved. A project manager may be authorised to arrange delivery but not to change the liability cap. Sections 186 and 187 of the Contract Act recognise express and implied authority, so job title alone does not resolve the question.
Preserve prior dealings where the same person approved changes and the company acted on them. Those records may matter to the authority analysis. Do not assume that an internal limit which the client never knew automatically defeats every external commitment. Where authority is contested, have counsel assess the full correspondence before issuing a categorical denial.
What if the invoice is now disputed under the new terms?
Build a version-based account: the agreed scope, delivery evidence, acceptance records, invoice and the disputed deduction. Ask the client to identify the term relied on and when you supposedly accepted it. Separate an admitted amount from a dispute over the balance, and check any contractual notice and dispute procedure promptly.
My review would follow one changed obligation through the whole record rather than starting with the newest PDF. Was it offered, accepted and performed, and by whom? That approach is useful both for negotiation and for a later claim. The related answer on indemnity clauses shows why a small-looking PO revision can alter exposure far beyond the invoice value.
- Original purchase order and the exact acceptance sent.
- Revised purchase order with every changed clause identified.
- Master agreement and its amendment and priority provisions.
- Delivery and project records showing which instructions were followed.
Where the client says the portal accepted the revision, obtain the audit record identifying the user, time and action. Check whether that user had contracting authority. A screen labelled approved may describe procurement processing rather than the legal assent the client alleges.