The default answer is that the loser pays. Section 31A of the Arbitration and Conciliation Act, 1996 states the general rule that the unsuccessful party shall be ordered to pay the costs of the successful party, and a tribunal or court that wants to depart from it must record reasons in writing. That rule governs arbitration costs in India only at the end, though. While the reference is running, both sides fund it in equal shares through deposits under Section 38, and the tribunal holds a lien on the award under Section 39 until its costs are paid.
So there are really three money questions in every arbitration: who advances the cash, what the arbitrators are entitled to charge, and who ultimately bears the bill once the award is made. They are answered by different provisions and they are decided at different times.
What the statute counts as costs
Section 31(8) says the costs of an arbitration shall be fixed by the tribunal in accordance with Section 31A. The Explanation to Section 31A(1) defines costs as the reasonable costs relating to the fees and expenses of the arbitrators, courts and witnesses, legal fees and expenses, any administration fees of the institution supervising the arbitration, and any other expenses incurred in connection with the arbitral or court proceedings and the arbitral award.
That definition is wider than most parties expect. It picks up counsel's fees, the institution's charges, expert and witness expenses, and the costs of related court proceedings such as a Section 9 application or a Section 11 petition. A party that keeps no record of these heads through a three year reference is not in a position to claim them at the end, and tribunals do notice the difference between a costs claim supported by invoices and one asserted in a paragraph of written submissions.
Three provisions carry the money side of a reference, and each of them bites at a different stage.
Section 31A
The rule on who ultimately bears the bill. The unsuccessful party pays the successful party's costs, and any departure from that must be supported by reasons recorded in writing.
Section 38
Who funds the reference while it runs. The tribunal fixes deposits as an advance towards costs, payable in equal shares, with separate amounts possible for claim and counter claim.
Section 39
The tribunal's security for payment. It holds a lien on the award until its costs are paid, and a party who thinks the demand unreasonable may apply to court under Section 39(2).
The default rule on arbitration costs in India, and how tribunals depart from it
Section 31A(2) sets the general rule that the unsuccessful party pays, while allowing a different order for reasons recorded in writing. Section 31A(3) lists what the tribunal must weigh: the conduct of all the parties, whether a party has succeeded partly, whether a party made a frivolous counter claim leading to delay, and whether a reasonable offer to settle was made by one party and refused by the other.
Section 31A(4) then gives the tribunal a menu rather than an all or nothing choice. It may order a party to pay a proportion of the other side's costs, a stated amount, costs from or until a certain date only, costs incurred before proceedings began, costs of particular steps, costs of a distinct part of the proceedings, and interest on costs from or until a certain date.
Key takeaway. Section 31A(5) makes an agreement that one party will bear the whole or part of the costs in any event valid only if it was made after the dispute arose. A clause in the original contract saying each side bears its own costs whatever happens does not survive that provision.
Who funds the arbitration while it is running
Section 38 is the provision that decides who writes cheques before the award. The tribunal may fix a deposit or supplementary deposit as an advance towards the costs referred to in Section 31(8), and where a counter claim has been filed it may fix separate amounts for the claim and the counter claim. The deposit is payable in equal shares by the parties. If one party does not pay its share, the other may pay it. If neither pays in respect of a claim or counter claim, the tribunal may suspend or terminate the proceedings in respect of that claim or counter claim. On termination, Section 38(3) requires the tribunal to render an accounting of deposits received and return any unexpended balance.
Two practical consequences follow. First, a respondent who refuses to fund the reference does not stall it. The claimant can pay both shares and add the amount to its costs claim. Second, a claimant who will not fund its own claim risks having that claim suspended while the counter claim proceeds.
Common mistake. Treating the deposit as the final cost. Deposits are advances towards costs, and supplementary deposits are common when hearings run longer than planned. Budget for the supplementary calls, not just the first one.
Arbitrator fees, the Fourth Schedule, and what ONGC v. Afcons decided
The Fourth Schedule to the Act sets model fees by reference to the sum in dispute. The principal slabs are set out below.
| Sum in dispute | Model fee under the Fourth Schedule |
|---|---|
| Up to Rs 5,00,000 | Rs 45,000 |
| Above Rs 5,00,000 and up to Rs 20,00,000 | Rs 45,000 plus 3.5 per cent of the claim amount over Rs 5,00,000 |
| Above Rs 20,00,000 and up to Rs 1,00,00,000 | Rs 97,500 plus 3 per cent of the claim amount over Rs 20,00,000 |
| Above Rs 1,00,00,000 and up to Rs 10,00,00,000 | Rs 3,37,500 plus 1 per cent of the claim amount over Rs 1,00,00,000 |
| Above Rs 20,00,00,000 | Rs 19,87,500 plus 0.5 per cent of the claim amount over Rs 20,00,00,000, with a ceiling of Rs 30,00,000 |
There is a further slab for sums above Rs 10,00,00,000 and up to Rs 20,00,00,000. The Note to the Schedule adds that a sole arbitrator is entitled to twenty five per cent over the fee in the table.
In Oil and Natural Gas Corporation Ltd v. Afcons Gunanusa JV, decided on 30 August 2022, the Supreme Court settled several of the arguments that used to consume the first year of a reference. Arbitrators cannot unilaterally issue binding and enforceable orders fixing their own fees, because that makes them a judge in their own cause. The tribunal can still apportion costs under Sections 31(8) and 31A and demand deposits under Section 38, but a finding on its own fees made without agreement is not enforceable in its favour. Its remedy is the lien under Section 39(1), and a party who thinks the demand is unreasonable may apply to court under Section 39(2).
The Court also held that the Fourth Schedule is not mandatory, so parties remain free to agree the fees or the method of fixing them. Where the Schedule has been made applicable to an ad hoc arbitration, the expression sum in dispute means the claim and the counter claim separately rather than cumulatively, so a separate fee may be charged for each and the ceiling applies separately to both. The ceiling of Rs 30,00,000 in the last entry applies to the total of the base amount and the variable component, and it applies to each individual arbitrator rather than to a three member tribunal as a whole.
Ad hoc or institutional: where the money actually goes
| Cost head | Ad hoc arbitration | Institutional arbitration |
|---|---|---|
| Arbitrator fees | By agreement, or by reference to the Fourth Schedule if adopted. Often negotiated at the first procedural hearing | Fixed by the institution's published schedule, as with the Delhi International Arbitration Centre rules |
| Administrative fee | None, but the parties absorb the administration themselves | A separate registration and administration charge |
| Venue, recording, secretarial | Billed separately and frequently underestimated | Usually bundled or scheduled |
| Deposits | Called by the tribunal under Section 38 | Called and held by the institution |
| Fee disputes | A live risk, which is what Afcons addressed | Rare, because the schedule is agreed in advance by adopting the rules |
| Time discipline | Depends on the tribunal and counsel | Rules typically impose timetables that shorten the reference |
The cheapest arbitration is not the one with the lowest arbitrator fee. It is the one that finishes. A reference that drifts across five years accumulates counsel fees, sitting fees and supplementary deposits that dwarf any saving at the appointment stage. Our note comparing institutional and ad hoc arbitration deals with the wider trade off, and the mechanics of appointment are covered in our note on appointment of an arbitrator under Section 11.
The cost consequences the statute builds in
Delay has a price for everyone. Under Section 29A(1), an award in a domestic arbitration must be made within twelve months of the completion of pleadings, extendable by six months with the parties' consent under Section 29A(3). Beyond that the mandate terminates unless the court extends time, and the proviso to Section 29A(4) allows the court, where it finds delay attributable to the tribunal, to reduce the arbitrators' fees by up to five per cent for each month of delay, after giving the arbitrator a hearing.
On the other side, Section 31(7)(b) provides that a sum directed to be paid by an award carries interest, unless the award directs otherwise, at two per cent higher than the current rate of interest prevalent on the date of the award, from the date of award until payment. Combined with the power in Section 31A(4)(g) to award interest on costs, that is a serious incentive for a losing party not to sit on an award while a Section 34 challenge is prepared.
Deadline warning. Section 29A is not a soft target. If the twelve month period and the six month consent extension both lapse without a court extension, the mandate of the arbitrator terminates, and everything spent up to that point is at risk of being spent twice.
Four statutory levers decide what delay and non payment cost each side once the award is in sight.
Twelve months, Section 29A(1)
A domestic award must be made within twelve months of the completion of pleadings. The clock starts when pleadings close, not when the dispute arose.
Six month consent extension
Section 29A(3) allows a further six months if the parties consent. Beyond that the mandate terminates unless the court extends time.
Fee cut for tribunal delay
The proviso to Section 29A(4) lets the court cut the arbitrators' fees by up to five per cent for each month of delay attributable to the tribunal, after hearing the arbitrator.
Interest under Section 31(7)(b)
A sum directed to be paid by an award carries interest at two per cent above the current prevalent rate on the date of the award, running from award until payment.
How to control what an arbitration costs you
- Fix the arbitrator's fees in writing at the first procedural hearing, and record whether the Fourth Schedule applies, whether the claim and counter claim are charged separately, and what a sitting is.
- Agree the ancillary heads at the same time: reading fees, cancellation charges for adjourned hearings, transcription and venue.
- Consider adopting institutional rules even in an ad hoc reference, so that a published fee schedule replaces a negotiation with your own tribunal.
- Keep a running costs ledger from day one, with counsel invoices, deposit receipts, institution charges and expert fees, so the Section 31A claim is evidenced rather than asserted.
- Make a written offer to settle if the case warrants it. Section 31A(3)(d) makes a reasonable offer that was refused a relevant circumstance in the costs order.
- Track the Section 29A clock from the date pleadings complete, and apply for extension before expiry rather than after.
- Object to a unilateral fee revision immediately and in writing. Afcons makes the point available, but a party that pays without protest for two years has a much weaker complaint.
- Plead costs properly in the statement of claim or defence, with the heads identified, so the tribunal is not left to improvise a figure at the end.
Indicative ranges
Any figure here is a planning range and not a quotation. Arbitrator fees in a domestic ad hoc reference are commonly anchored to the Fourth Schedule, so the statutory ceiling of Rs 30,00,000 per arbitrator marks the top of that scale for very large claims, with the sole arbitrator uplift of twenty five per cent on top. Institutional administration charges are usually a small fraction of the arbitrator fees and are published, so they can be modelled precisely before you file. Counsel fees are the largest and least predictable head in most references. On timing, a straightforward domestic arbitration that stays within Section 29A tends to run from twelve to eighteen months from the completion of pleadings, while a document heavy construction or shareholder dispute with extensions and interlocutory applications commonly runs longer. A Section 34 challenge and any Section 37 appeal add their own time and their own costs, which is why the costs claim should be framed to cover related court proceedings as Section 31A permits. Our note on setting aside an arbitral award under Section 34 covers that stage.
A note from practice
The single most avoidable cost in Indian arbitration is the fee argument itself. Parties reach the first procedural hearing focused on the timetable, treat fees as an awkward subject to be settled later, and then spend the next year exchanging letters about sitting fees and reading fees while the merits stand still. Afcons removed much of the legal uncertainty, but it cannot supply the agreement that should have been recorded on day one. The second avoidable cost is a costs claim that arrives unsupported. Section 31A gives a tribunal wide discretion, and discretion tends to follow the party that has done the arithmetic. Anyone facing a live reference should take advice on their own contract and rules, because whether the Fourth Schedule applies at all depends on what the arbitration agreement and any adopted institutional rules actually say. You can read more about our work in arbitration and alternative dispute resolution.
Related guides and where to get help
- Section 9 vs Section 17 Arbitration: Interim Relief
- Institutional vs Ad Hoc Arbitration in India: A Guide
- Judicial Interference in Arbitration in India: Explained
Frequently Asked Questions
Does the losing party always pay the winner's costs?
No, but that is the starting point. Section 31A(2) states the general rule that the unsuccessful party pays, and allows a different order only for reasons recorded in writing. Partial success, conduct, a frivolous counter claim and a refused settlement offer are all circumstances the tribunal must consider.
Can our contract say each side bears its own costs?
Only if that agreement was made after the dispute arose. Section 31A(5) provides that an agreement that a party is to pay the whole or part of the costs in any event is valid only if made after the dispute in question has arisen.
What happens if the other side refuses to pay its share of the deposit?
Under the proviso to Section 38(2) you may pay that share yourself and claim it back as part of your costs. If neither side pays in respect of a claim or counter claim, the tribunal may suspend or terminate the proceedings in respect of it.
Can arbitrators fix their own fees?
Not unilaterally. In ONGC v. Afcons Gunanusa JV the Supreme Court held that a unilateral determination is not binding and enforceable, though the tribunal may apportion costs under Sections 31(8) and 31A, call deposits under Section 38, and exercise a lien on the award under Section 39(1).
Is the Fourth Schedule compulsory?
No. The Supreme Court has held it is not mandatory and that parties may agree the fees or the modalities for fixing them. It becomes the yardstick where the parties or the court adopt it.
Is the Rs 30,00,000 ceiling per arbitrator or for the whole tribunal?
Per arbitrator. The Court held the ceiling in the last entry applies to the total of the base and variable components and applies to each individual arbitrator rather than to a tribunal of three or more as a whole, with a sole arbitrator entitled to twenty five per cent over that.
Can the tribunal refuse to hand over the award until it is paid?
Yes. Section 39(1) gives the tribunal a lien on the award for unpaid costs of the arbitration, subject to any contrary provision in the arbitration agreement. Section 39(2) lets a party apply to court, which may order delivery on payment of the demanded costs into court and then decide what is reasonable.
Has the arbitration law changed recently?
The governing statute remains the Arbitration and Conciliation Act, 1996 as amended in 2015, 2019 and 2021. A draft amendment Bill circulated for consultation in 2024 proposed further changes, but a draft is not law and it does not govern any reference until it is enacted and notified.
This article is general information and not legal advice. What an arbitration costs, and who bears it, depends on the arbitration agreement, the rules adopted and the conduct of the reference.






