Yes, for what the builder is failing to do now, and with care for the refund. Section 31 of the Real Estate (Regulation and Development) Act, 2016 lets any aggrieved person complain to K-RERA for "any violation or contravention" of the Act, the rules or the regulations, and three of the builder's duties do not wait for your possession date: the quarterly updates under Section 11(1), the seventy percent account under Section 4(2)(l)(D) and the stage-wise schedule that Section 19(2) entitles you to know. The refund and delay interest under Section 18(1)(a) are measured against the date in your agreement, and on 6 June 2023 a K-RERA bench dismissed a refund complaint filed eleven months before that date as premature. On 9 October 2026 the Maharashtra Real Estate Appellate Tribunal allowed an appeal against a similar dismissal, in part, and ordered a refund after the agreed date had passed while the case was pending.
Part of the RERA and homebuyer disputes practice at S Jain & Attorneys, Bangalore.
This guide is for a buyer in a registered Karnataka project whose site has gone quiet and whose possession date is still months away. If the registration has already lapsed, read the guide on a stalled project and a Section 8 takeover instead.
| What you see | Can K-RERA hear it now? | The provision |
|---|---|---|
| No quarterly update for a quarter that ended more than fifteen days ago | Yes | Section 11(1), Rule 15(1)(D), Regulation 29(4) |
| No account of where the money went | Yes, ask for an inquiry | Section 4(2)(l)(D), Section 35 |
| The builder will not give the stage-wise schedule | Yes | Sections 11(3) and 19(2) |
| A continuing breach you want stopped before the hearing | Yes, ask for an interim order | Section 36, Regulation 17 |
| The site is shut and you want your money back | Risky: a K-RERA bench dismissed such a claim as premature in 2023 | Section 18(1)(a) |
| The agreed date, with any grace period, has passed | Yes, refund or delay interest | Section 18(1) and its proviso |
Four points decide what you can file today.
Quarterly updates are due
Rule 15(1)(D) makes the builder upload construction status with photographs of each building and floor within fifteen days after every quarter ends.
The seventy percent account
Section 4(2)(l)(D) keeps seventy percent of buyers' money in a separate account, withdrawn only in proportion to completion on certificates.
Your right to the schedule
Section 19(2) entitles you to know the stage-wise time schedule of completion, and Section 11(3)(b) makes the builder provide it at booking.
Refund waits for the date
Section 18(1)(a) runs from the date in your agreement, and a K-RERA bench dismissed an early refund complaint as premature in June 2023.
Is a complaint before the possession date premature?
It depends on what the complaint asks for. Section 31 carries no date: it reaches "any violation or contravention" of the Act or the rules and regulations, and a quarterly update never filed is a contravention once the fifteen days after the quarter have run. The refund is different. Section 18(1)(a) makes the builder liable where he fails to complete or give possession "in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein", so a refund claimed before that date has nothing to measure against.
One K-RERA bench has taken that line. Two buyers in the same stalled Devanahalli project filed complaints on the same day, 25 July 2022, before the same bench, after the builder stopped paying their pre-EMI under a subvention scheme, and both sought a refund by the time they were heard. Their agreements promised possession by December 2022 with six months' grace, that is by the end of June 2023. On 6 June 2023, in complaint CMP/220725/0009803, the bench held the complaint filed "11 months early and premature in nature", dismissed it as not maintainable and gave liberty to file again after June 2023. On 26 July 2023, with the date passed and no premature objection recorded, it allowed complaint CMP/220725/0009802 with a refund and interest at MCLR plus two percent, recording that the builder was "nowhere near completion". The pre-EMI side is covered in the guide on a builder who stops paying pre-EMI.
In Maharashtra the question reached the appellate tribunal. A buyer whose builder stopped servicing his loan interest complained before his possession date of 31 December 2021, and MahaRERA dismissed the complaint as premature on 2 September 2021. On 9 October 2026, in Appeal No. AT006000000053435 of 2022 against Man Realty Ltd, HDFC Bank and Purva Oak Pvt Ltd, the Tribunal partly allowed the appeal. It held that "the simple fact that the complaint was instituted before the expiry of the contractual date of possession cannot be the sole determinant" of relief, that "An appeal is a continuation of original proceedings", and that because the date had passed undelivered meanwhile, the refund could not be rejected solely as premature. It added that the bank's notice had not by itself made the claim accrue: what mattered was whether the agreed date had expired when the complaint was filed "or whether any other legally sustainable basis for invoking Section 18 has arisen".
No K-REAT decision on the point was found at the time of writing. Our reading of the Karnataka orders, which no court has stated as a rule: breaches that have already happened can be complained of now, while a refund claim filed early risks dismissal with liberty if decided before the date. The Maharashtra buyer waited five years from the dismissal to the appeal judgment.
Key takeaway. The premature objection attacks a refund claimed before the agreed date. It should not answer a complaint about quarterly updates never filed or a project account nobody can see. Keep the two kinds of prayer apart.
What can I complain about now: stopped work, missed quarterly updates, the seventy percent account?
Every duty the builder is already breaking, and a silent site usually means several. Section 11(1) of the RERA Act requires the builder to keep the project's page on the K-RERA portal current, including the "quarterly up-to-date status of the project". Rule 15(1)(D) of the Karnataka Rules, 2017 fixes fifteen days from the expiry of each quarter and requires the status of construction of each building and floor, with photographs. Under Regulations 3(1)(ii) and 29(4) of the K-RERA (General) Regulations, 2022, each quarterly return carries certificates of the chartered accountant, architect and engineer in Forms 4, 5 and 6, and the project bank account statement, certified by the chartered accountant, is appended to Form 4.
The money rule is Section 4(2)(l)(D). Seventy percent of the amounts realised from buyers must sit in a separate account with a scheduled bank, used only for construction and land cost, withdrawn "in proportion to the percentage of completion of the project" and only after an engineer, an architect and a chartered accountant certify it, with the accounts audited within six months after each financial year. Regulation 29 makes it a no-lien account. A site where nothing moves while withdrawals continue is what the certificates exist to catch, and Section 35 lets the Authority call for the statements and appoint someone to inquire. Separately, Section 11(3)(b) makes the builder give you the stage-wise schedule at booking.
The consequences are regulatory first: a penalty of up to five percent of the estimated project cost under Sections 60 and 61, directions "binding on all concerned" under Section 37, and revocation under Section 7 for a default. Your own proved loss is compensated under Section 18(3), before the adjudicating officer.
Common mistake. Filing a complaint whose only prayer is a refund, months before the agreed date. That is the complaint K-RERA dismissed in June 2023. Ask first for the missing quarterly updates, the account statements and an inquiry, and seek the Section 18 relief when the date passes.
Can I withdraw and take a refund before the date?
Usually not. Section 18(1)(a) is measured against the agreed date, and the June 2023 order dismissed such a claim as premature. Clause (b) is a second trigger: failure "due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason". A builder who has stopped work but keeps his registration and says he will resume has not plainly discontinued his business, and we found no Karnataka order treating a stalled site, before the date, as discontinuance, so treat that argument as open.
Your agreement may give you an exit of its own: read the buyer's termination clause and what it forfeits. Once the date passes, the refund is of the money you actually paid, with interest from each payment at "the State Bank of India highest marginal cost of lending rate plus two percent" under Rule 16, payable within sixty days under Rule 17, as the guide on the K-RERA interest calculation works through. In the Maharashtra case the Tribunal directed a refund of Rs 1,85,99,612 less Rs 14,10,604 paid towards taxes, with interest at the highest SBI MCLR plus two percent from the dates of payment, a deed of cancellation within forty-five days so the stamp duty and taxes could be reclaimed, failing which that sum too, and costs of Rs 25,000.
Deadline warning. Diary the agreed date with its grace period. Section 18(1) makes the builder liable "on demand", so send a written demand for the refund or delay interest the day after it passes, and place it on record in any complaint already pending.
What interim orders can K-RERA make under Section 36?
K-RERA can restrain a continuing or threatened breach while it inquires. Section 36 applies where, "during an inquiry", the Authority is satisfied that an act in contravention "has been committed and continues to be committed or that such act is about to be committed", and lets it restrain the promoter "until the conclusion of such inquiry or until further orders", without notice where necessary. Regulation 17 allows "such ad-interim or interim order, as the Authority may consider appropriate at any stage of the proceedings".
Section 36 is worded as a restraint. On our reading it can stop an act, such as withdrawals from the project account that the certificates do not support, but does not by its words order work to resume. For the rest, ask for directions under Section 37 to upload the missing updates with Forms 4 to 6, and an order under Section 35 to produce the account statements. An interim prayer needs facts showing a continuing breach, not only a fear that the project will fail.
Does the builder's registration extension move my possession date?
No, on the Maharashtra Tribunal's reasoning. K-RERA's orders on extensions are in the guide on the interest calculation. Under Section 5(3) the registration lasts for the period the builder declares under Section 4(2)(l)(C), and Section 6 allows extension for force majeure or, "in reasonable circumstances, without default on the part of the promoter", for not more than one year in aggregate. MahaRERA had extended the Man Realty project from time to time, to 30 April 2027 on the latest record, and the Tribunal held that "The extension of the project completion date under RERA registration does not rewrite or alter the contractual obligations under the Agreement for Sale". Both 2023 Karnataka orders record a nine-month extension of the registration to 30 September 2023 and still worked from the agreement's June 2023 date.
Your own paper can move the date. Read your agreement's force majeure clause, and read the guide on a settlement addendum that moves the date before signing one.
What if a new promoter takes over the project?
The incoming promoter takes on your agreement. Section 15(1) bars a transfer of the majority rights and liabilities without the prior written consent of two-thirds of the allottees and the Authority's prior written approval, and Section 15(2) makes the incoming promoter "independently comply with all the pending obligations" under the Act and the earlier promoter's agreements, with no extension of time. In the Maharashtra case Purva Oak Pvt Ltd, on its own account, took the project under a SARFAESI sale certificate of 7 June 2024, and MahaRERA approved the transfer under Section 15 on 13 August 2024. Purva Oak argued that Section 15 covers only voluntary transfers. Relying on that approval and the companies' project management agreement, the Tribunal held it bound by Section 15(2) and directed the refund against it alone. Consent itself is covered in the guide on a request to consent to a new promoter.
Sometimes the silence means insolvency. Under IBBI circular No. IBBI/CIRP/110/2026 of 30 October 2026, the interim resolution professional or resolution professional of a builder with a real estate project must, within seven days of appointment, display a conspicuous signboard at each project site and notice boards at its offices, with his name and contact details. If the gate carries one, read the guide on a homebuyer's claim in Form CA first.
What should I collect and file this month?
Build the record now, file for the breaches that exist, and keep the refund for the date.
- Download the project page from the K-RERA portal: the registration certificate, the current completion date and any extension, and the quarterly updates. Take a dated screenshot of every quarter with no update.
- Photograph the site from the same points on a fixed day each week.
- Read your agreement for the possession date and grace period, the force majeure clause, your termination clause and the interest clause.
- List every payment from receipts and bank statements, including loan disbursements paid to the builder. The claim is what you actually paid.
- Write to the builder asking, within fifteen days, for the stage-wise schedule, the latest quarterly certificates and the reason work has stopped.
- Check the site gate and the builder's offices for an insolvency signboard.
- File Form N under Rule 29(1), fee Rs 1,000, praying for directions to upload the missing updates with Forms 4 to 6, production of the account statements, an inquiry under Section 35, an interim order where a continuing breach is shown, and a penalty under Section 61, and stating that you will seek Section 18 relief when the date passes.
- The day after the date and grace period pass, send the Section 18 demand and place it on record, or file the refund complaint.
In our practice two things go wrong. Some buyers wait in silence, and when the date passes they have no record of which quarters were missing, because the page may since have been filled in. Others file a refund-only complaint the month the labour leaves and get a dismissal with liberty a year later. Those who do better file for the breaches that exist, keep paying what the agreement requires, and have the refund demand ready for the date.
Four facts to keep in view.
Fifteen days per quarter
Rule 15(1)(D) gives the builder fifteen days after each quarter to upload construction status with photographs of every building and floor.
Same filing day, two outcomes
Of two complaints filed on 25 July 2022 in one project, one was dismissed as premature in June 2023 and the other allowed in July 2023, after the date.
Extension is not your date
The Maharashtra Tribunal held in October 2026 that extending a project's registration does not rewrite or alter the obligations under the agreement for sale.
The new promoter is bound
Section 15(2) makes an incoming promoter comply with the earlier promoter's pending obligations, with no extra time to complete the project.
Frequently Asked Questions
The builder says my complaint is premature because the possession date is next year. Is he right?
Only about a refund or delay interest under Section 18(1)(a), which runs from the date in your agreement. A complaint about missed quarterly updates, the seventy percent account or a refused schedule concerns breaches that have already happened, and Section 31 covers any violation of the Act, rules or regulations.
Does one missed quarterly update entitle me to a refund?
No. It is a contravention that can lead to directions under Section 37 and a penalty of up to five percent of the estimated project cost under Section 61, and it is evidence for your later Section 18 claim. The refund itself turns on the agreed date.
Can I see the seventy percent account myself?
The Regulations require the account statement, certified by the chartered accountant, to be appended to Form 4 in every quarterly return. If the project page does not show it, ask the Authority to call for the statements under Section 35.
The portal shows the builder's registration extended by a year. Does my possession date move?
Not on the Maharashtra Tribunal's October 2026 reasoning, which held that an extension of the project's registration does not alter the agreement. Two K-RERA orders of 2023 worked from the agreement's date despite a recorded extension. On that reasoning, your date moves only if your agreement's own clauses, or a document you sign, move it.
Can I stop paying instalments until work restarts?
Not unilaterally. Section 19(6) obliges you to pay as the agreement specifies, Section 19(7) charges interest on delay, and Section 11(5) lets the builder cancel only in terms of the agreement. Read the guide on cancellation for missed instalments before you hold back a payment.
Can the buyers in my project complain together?
Yes. The Explanation to Section 31 includes an association of allottees, or a registered voluntary consumer association, in "person", so a registered buyers' association can file in its own name. Individual buyers can also file their own complaints at the same time.
What does a K-RERA complaint cost and how long does it take?
Rule 29(1) prescribes a fee of Rs 1,000 for Form N. The two Karnataka complaints described in this guide took about ten and twelve months from filing to order, and lawyers' fees are separate, so treat every figure as indicative.
What if the builder is in insolvency?
Since 30 October 2026 an IBBI circular requires the insolvency professional to display a signboard at each project site and notice boards at the builder's offices within seven days of appointment. If you see one, read the guide on Form CA before taking any other step, because the insolvency process has its own claim form.
This article is for general informational purposes only and does not constitute legal advice. Consult a qualified advocate for advice on your specific situation.