Yes. You can file a K-RERA complaint online from Mysuru, Mangaluru, Hubballi-Dharwad or Belagavi without a trip to Bengaluru: Regulation 11(1) of the Karnataka Real Estate Regulatory Authority (General) Regulations, 2022 requires Form N and Form O complaints to be lodged on the Karnataka RERA web portal with the fee, which is paid only by e-payment. What you cannot do from home is move the hearings. Rule 23(1) of the Karnataka Real Estate (Regulation and Development) Rules, 2017 places the Authority's office at Bengaluru, and although Rule 23(5) lets the Chairperson order sittings elsewhere, no such order was found on the Authority's portal. So file and follow the case online, and authorise an advocate under Section 56 of the Real Estate (Regulation and Development) Act, 2016 for the dates you cannot attend.
Part of the RERA and homebuyer disputes practice at S Jain & Attorneys, Bangalore.
This guide is for a buyer outside Bengaluru whose Karnataka builder has missed the possession date or will not refund, and it does not decide whether you should stay in the project or withdraw.
Can I file a K-RERA complaint online without coming to Bengaluru?
Yes, the filing itself is wholly online. Regulation 11(1) says complaints in Form N or Form O "shall be lodged in the Karnataka RERA web portal, along with the fee specified", and the Authority's complaint registration manual covers the sequence from creating a login to receiving a complaint number. The fee is paid through the Treasury Unified Gateway by net banking from a listed bank. Rules 29(1) and 30(1) still describe the fee as a demand draft, but the manual states that the Authority accepts payment only through e-payment.
A Karnataka RERA complaint is not tied to where you live: Section 31(1) of the Act lets "any aggrieved person" complain to the Authority or the Adjudicating Officer. Once the complaint is lodged, Regulation 11(3) requires an authorised officer to scrutinise it and to communicate any defects within seven days. In the live form those queries go to the complainant's e-mail, so give one you read daily.
In short, this is what a buyer can do from home:
File on the portal
Form N and Form O complaints are lodged on the Karnataka RERA web portal with the fee, under Regulation 11(1) of the 2022 Regulations.
Pay the fee online
The fee is Rs 1,000 for each form under Rules 29(1) and 30(1), and the portal accepts it only through e-payment.
Track every date
The complaint status page, the daily cause lists and the daily orders on the portal let you follow each date from home.
Receive the order
Regulation 19(2) gives each party a copy of the final order free of cost, either by post or in person.
Which form do I need: Form N to the Authority or Form O to the Adjudicating Officer?
Use Form N for a refund with interest or for interest on the delay, and Form O only for compensation. Rule 29(1) sends complaints about violations of the Act, the Rules or the Regulations to the Authority in Form N, except matters for the Adjudicating Officer, and Rule 30(1) sends compensation claims under Sections 12, 14, 18 and 19 to the Adjudicating Officer in Form O. The Supreme Court drew the same line in Newtech Promoters and Developers v State of UP (2021, paragraph 86), a passage K-RERA reproduces in its notification of 10 March 2022 on additional benches.
| Point | Form N, to the Authority | Form O, to the Adjudicating Officer |
|---|---|---|
| Rule | Rule 29(1) | Rule 30(1) |
| What it is for | Any violation of the Act, Rules or Regulations, other than matters for the Adjudicating Officer | Compensation under Sections 12, 14, 18 and 19 |
| For a delayed flat or plot | Refund with interest if you withdraw, or interest for every month of delay if you stay (Section 18(1)) | Compensation claimed under Section 18, decided as a separate claim |
| Who decides | The Authority, sitting as a full bench or in the benches it constitutes | A judicial officer who is or has been a District Judge (Section 71(1)) |
| Fee | Rs 1,000 | Rs 1,000 |
| Where it is lodged | Karnataka RERA web portal (Regulation 11(1)) | Karnataka RERA web portal (Regulation 11(1)) |
Wanting both interest and compensation means two forms before two forums, each with its own Rs 1,000 fee.
What should I keep ready before I open the online form?
Scan everything first, because the form does not save a page until you move to the next one, and a timeout loses what you have entered. The live form asks for:
- your photo identity document as a file of 1 MB or less, an Indian mobile number and an e-mail, and a mobile number and e-mail for each builder you name
- four photographs of the project, which the form treats as compulsory
- a payment schedule with one row for every payment, giving the amount, the mode and the date
- your supporting documents, such as the agreement for sale, allotment letter, receipts, demand letters and the builder's messages about the possession date, each as a PDF or image with a caption
Form N includes a declaration that the matter is not pending before any court of law, authority or tribunal, and ends with a verification that nothing material has been suppressed. If you have already started proceedings anywhere else about the same flat, take advice before you make that declaration.
How to file a RERA complaint in Karnataka, step by step
This follows K-RERA's complaint registration manual, with what the live form adds.
- Open rera.karnataka.gov.in, choose Complaint Registration and register as a new user with your name, phone number and e-mail. Log in with the details sent to that e-mail and set a new password using the one-time password.
- Fill in the complainant details, the photo identity document and, if an advocate is acting for you, the advocate's details. Attach the four project photographs and the supporting documents, each with its caption.
- On the respondent page, choose who the complaint is against, the section and the nature of the complaint, then select the registered project from the drop-down list, or type the project and promoter names if it is unregistered.
- Enter the payment schedule, one row for each payment.
- Write the complaint subject, the facts and the relief you seek, and fill in the builder's details.
- Check the preview page and print a copy.
- Pay the fee through the Treasury Unified Gateway by net banking, and note the payment reference number.
- Keep the complaint number from the confirmation page to track the complaint.
Where does K-RERA sit, and does it hold hearings in Mysuru, Mangaluru, Hubballi-Dharwad or Belagavi?
K-RERA sits in Bengaluru. Rule 23(1) locates the office at Bengaluru, and the Authority's circulars give the address as 2nd Floor, Silver Jubilee Block, Unity Building, CSI Compound, 3rd Cross, Mission Road, Bengaluru 560027. Rule 23(5) says the Authority "shall ordinarily have sittings at its headquarters and at such other places as the Chairperson may by general or special order specify". But on 23 November 2026 neither the circulars nor the public notifications on the portal carried any such order, and the 2022 notification constituting additional benches fixes no place outside Bengaluru.
The other routes run from Bengaluru too. The 2019 procedure places K-RERA's conciliation cell in the Authority's office, on Saturdays, and the National Lok Adalat of 19 September 2026 was notified for the Authority's premises. The Karnataka Real Estate Appellate Tribunal (K-REAT), whose jurisdiction covers the whole of Karnataka, works from the same Unity Building compound. The pages on RERA disputes in Mysuru and Mangaluru and Udupi look at what recurs in those districts.
Key takeaway. Filing, paying and tracking happen online. Hearings happen at Mission Road, Bengaluru. The bridge is an advocate you authorise under Section 56, with the authorisation and written consent in original under Rule 29(4).
Do I have to attend every hearing, or can an advocate appear for me?
You do not have to attend every date yourself. Section 56 of the Act says the applicant "may either appear in person or authorise" legal practitioners, chartered accountants, company secretaries or cost accountants to present the case before the Authority, the Adjudicating Officer or the Appellate Tribunal. Rule 29(4) requires the authorisation and the representative's written consent, "both in original", to be appended to the complaint or the reply, and Regulation 13 requires the person appearing for you to file a memorandum of authorisation before the proceedings and obtain an acknowledgement. As the complaint goes in online, ask the registry how it wants the originals lodged, and do it before the first date.
The procedure under Rule 29(2) is summary. The builder gets notice with the particulars and the documents, may reply within the time the notice fixes, and the notice names a date and time for the hearing. The Authority may inquire into the complaint "on the basis of documents and submissions", and in taking evidence it is not bound by the Indian Evidence Act. But under Rule 29(2)(j), if any person fails to appear, the Authority may proceed in that person's absence after recording its reasons, so never let a listed date pass with nobody there.
Can I join a K-RERA hearing online by video?
Do not plan on it. No rule, regulation, circular or notice now in force was found on the portal that lets parties join a K-RERA hearing online. The only mention of video conferencing in the 2022 Regulations, Regulation 7(6), concerns meetings of the Authority's own members. The Authority's daily cause list gives each complaint a hearing date, time and bench, but no link to join online.
So ask first. Call the numbers on the Authority's contact page, 080-22249798 or 080-22249799, and ask the registry before your first date whether parties may join that bench online and, if so, how. If the answer is no, the authorised advocate is the way to avoid the journey.
How do I follow my complaint from home between hearing dates?
Use the portal's public pages, which need no login. The complaint status page lets you search by complaint number, temporary complaint number, project name or promoter name. The Authority and the Adjudicating Officer each have a daily cause list and a daily orders page, and the Authority's cause list shows each complaint's hearing date, time and bench. On 23 November 2026 the status page counted 14,040 complaints, of which 12,224 were disposed.
Regulation 19(2) entitles you to a free copy of the final order, by post or in person, and the date a copy reaches you starts the sixty days for an appeal under Section 44(2).
Can I settle without a full hearing, through K-RERA's conciliation cell or a Lok Adalat?
Possibly, but both routes also run from Bengaluru. K-RERA formed a Conciliation and Dispute Resolution Cell by a notification of 27 November 2019, citing Section 32(g) of the Act. The party starting conciliation files an online application, e-mailed automatically to the other side, which must convey its consent within seven days, and the first party then pays a fee of Rs 500. Both parties are expected to attend in person or through authorised representatives who can take decisions. A settlement is signed as a consent agreement by the parties and the conciliators, and if conciliation fails the dispute can still be pursued before K-RERA. A complaint already being heard can be referred to the cell only with the consent of both parties.
The procedure dated 25 November 2019 gives five days for consent, not seven, and calls the Rs 500 fee non-refundable. The portal still links to a conciliation login page, but confirm with the registry both the time limit and whether the cell is taking applications today.
The Lok Adalat route has a fuller record. K-RERA's notifications page lists National Lok Adalat sittings from 2022 to 2026, and the notification for 19 September 2026 covered refund, compensation, interest for delay in possession, amenities and permissible execution proceedings. The list of advantages published with that notification says parties can approach the Lok Adalat through their advocates or in person. On 23 November 2026 the Authority's published Complaints Realization List had 1,074 entries, and 703 of them carry a remark that the matter was settled or disposed of before or in a Lok Adalat.
How much interest will the builder owe, and how soon must a refund be paid?
Interest runs at the rate Rule 16 prescribes, which is "the State Bank of India highest marginal cost of lending rate plus two percent", and Rule 17 requires any refund with interest and compensation to be paid "within sixty days from the date on which such refund ... becomes due". Section 18(1) gives the choice behind those figures. If you withdraw, the builder must return the amount it received with interest. If you stay, the proviso entitles you to interest for every month of delay until possession is handed over. The guide to the K-RERA delay interest calculation works through the rate and the dates, and the guide to builder delay and a homebuyer's rights compares a refund with staying on.
What happens if the builder does not pay after the order?
You start enforcement on the portal, and the Authority carries it to the revenue authorities. Section 40(1) makes unpaid interest, penalty or compensation recoverable as arrears of land revenue, and Rule 25 applies the Karnataka Land Revenue Act, 1964 to that recovery. Under K-RERA's circular RERA/REVENUE/TAH/05/2026 of 28 July 2026, the Authority writes to both sides about compliance sixty days after the order. If the builder has not complied, you file an enforcement petition on the portal with an up-to-date memo of calculation. Both sides are called to appear within two weeks of the petition being registered and numbered, the builder gets two weeks to comply, and a builder that still has not paid a money award must file an affidavit of its assets, bank accounts included, within two weeks. If that fails too, a revenue recovery certificate goes to the office of the jurisdictional Deputy Commissioner for attachment and auction.
Directions that are not about money, such as a direction to hand over possession, are enforced under Section 40(2) and Rule 26 like a decree of the principal civil court. If the Authority cannot execute such an order, Rule 26 lets it send the order to the principal civil court where the project is located, or where the builder resides or carries on business, which for a Mysuru or Belagavi project can mean a court in that district. Do not file an execution petition in your local civil court yourself. On 31 October 2025 the Karnataka High Court quashed execution petitions that homebuyers had filed in the City Civil Court on K-RERA orders, holding that such an order cannot culminate in a decree in the classical sense (W.P. 17821/2025 and connected petitions). It said the executing court can be approached only in exceptional circumstances, after every effort to get the order executed before the Tahsildar as arrears of land revenue has completely failed. The guide to executing a RERA order through the revenue recovery certificate covers the Deputy Commissioner stage.
Can the builder or I appeal, and where does the appeal go?
Either side can appeal to K-REAT within sixty days of receiving a copy of the order, and only a builder has to deposit money first. Section 44(2) fixes the sixty days and lets the Tribunal admit a later appeal for sufficient cause, and Rule 33 sets a fee of Rs 5,000 and prescribes Form R. The K-REAT filing page on the portal says the appeal is e-filed in Form R, the memorandum and annexures are also furnished in triplicate at the Tribunal's filing counter, and an advocate's vakalath with the welfare fund stamp is filed there. Originals or authenticated copies of the uploaded documents must also be furnished at the counter or by registered post. Rule 33(6) makes appearance on every hearing date "obligatory on the parties or their agents". If the appellant does not appear, the Tribunal may dismiss the appeal for default or decide it on merits, and if the other side does not appear, it may decide the appeal ex parte. A buyer who lives outside Bengaluru must attend each date or have an authorised representative, such as an advocate, attend for them.
Under the proviso to Section 43(5), a promoter's appeal "shall not be entertained" until it deposits at least thirty per cent of any penalty, or a higher percentage the Tribunal fixes, or the total amount payable to the allottee with interest and compensation, or both. The Act puts no such condition on a buyer's appeal. Section 58 then allows an appeal to the High Court within sixty days of the Tribunal's decision being communicated, only on the grounds in Section 100 of the Code of Civil Procedure, 1908, and none from an order made with the consent of the parties. The guide on a builder's appeal and the pre-deposit explains what becomes of that deposit.
Deadline warning. The sixty days for an appeal run from the date a copy of the order is received, not from the date you hear of it. Note the day the copy reaches you. A later appeal needs an application, supported by an affidavit, showing sufficient cause.
What should a buyer far from Bengaluru get right at the start?
When the buyer lives several hours from Mission Road, the complaint has to carry the case on paper. I would rather file a complaint whose payment schedule ties to the bank entries, whose facts quote the possession clause of the agreement, and whose relief states how the interest is to be worked out, than one that leaves things to be explained at the hearing, because the Rules let the Authority inquire on documents and submissions. The second thing to settle on the first day is who will appear. An authorisation signed in a hurry the evening before a listed date is how dates get missed, and a missed date can mean the Authority going ahead without you.
Common mistake. Treating the online form as a short summary and leaving the payment history incomplete. The form asks for every payment with its amount, mode and date, and Section 18(1) measures a refund by the amount the builder received, so list every payment and keep the bank entries.
After the order, the timeline in short:
Sixty days to pay
Rule 17 requires a refund with interest and compensation to be paid within sixty days from the date it becomes due.
Petition on the portal
Under the circular of 28 July 2026 you file an enforcement petition on the portal with an up-to-date memo of calculation.
Recovery certificate
If the builder still does not pay, a revenue recovery certificate goes to the jurisdictional Deputy Commissioner for attachment and auction.
Appeal within sixty days
An appeal to K-REAT lies within sixty days of receiving the order's copy, and only a promoter must deposit money first.
Frequently Asked Questions
Do I need to visit the K-RERA office to file my complaint?
No. Regulation 11(1) requires Form N and Form O complaints to be lodged on the Karnataka RERA web portal, and the Rs 1,000 fee is paid online. The confirmation page gives you the complaint number to track it.
What is the fee for a Karnataka RERA complaint?
Rs 1,000 for a complaint to the Authority in Form N under Rule 29(1), and Rs 1,000 for a compensation complaint to the Adjudicating Officer in Form O under Rule 30(1). Under a K-RERA circular of 11 August 2020, co-complainants each pay Rs 1,000 unless they are all members of a single registered association.
Will K-RERA hear my complaint in my own district?
Plan on Bengaluru. Rule 23(5) allows sittings at other places by a general or special order of the Chairperson, but no such order was found on the K-RERA portal on 23 November 2026.
Can I attend the hearing by video call from Mysuru or Mangaluru?
No official source in force today was found that allows it. Ask the registry on 080-22249798 or 080-22249799 before your first date, and authorise an advocate under Section 56 if you cannot travel.
What happens if nobody appears for me on a hearing date?
Rule 29(2)(j) allows the Authority to proceed in the absence of a person who fails to appear, after recording its reasons. If you cannot attend, make sure the advocate you have authorised does.
Can buyers from the same project file one complaint together?
Section 31 counts an association of allottees as a person who may complain. Under the 2020 circular a registered association files on a single Rs 1,000 fee, while an unregistered group pays Rs 1,000 for each individual in it.
How long do I have to appeal against a K-RERA order?
Sixty days from the date you receive a copy of the order, under Section 44(2). K-REAT can admit a later appeal if it is satisfied there was sufficient cause, and its filing page asks for an application supported by an affidavit setting out the facts.
Does the builder have to deposit money before its appeal is heard?
Yes. The proviso to Section 43(5) bars a promoter's appeal from being entertained until it deposits at least thirty per cent of any penalty, or a higher percentage the Tribunal fixes, or the total amount payable to the allottee with interest and compensation, or both.
Who recovers the money if the builder ignores the order?
If the builder still does not pay after your enforcement petition, K-RERA issues a revenue recovery certificate and forwards it to the office of the jurisdictional Deputy Commissioner for attachment and auction, under its circular of 28 July 2026.
This article is for general informational purposes only and does not constitute legal advice. Consult a qualified advocate for advice on your specific situation.
Related Guides
- How Much Delay Interest Does the Builder Owe Me? The K-RERA Calculation at SBI MCLR Plus Two Percent
- The Builder Has Not Paid My RERA Order: Execution, the Revenue Recovery Certificate and the Deputy Commissioner in Karnataka
- The Builder Has Appealed My RERA Order: Pre-Deposit, Stay and the Karnataka Tribunal
- Builder Delay and Fraud: How Homebuyers in India Can Fight Delayed Possession and Recover Compensation