RERA Lawyer for Tumakuru, Kolar and Chikkaballapura Buyers

We act for buyers of layout plots, villa plots and homes in Tumakuru, Kolar and Chikkaballapura districts when a developer holds on to a booking amount, misses the completion date, leaves the layout incomplete or defaults on a refund it signed up to, before K-RERA, the Karnataka Real Estate Appellate Tribunal and the consumer commissions.

We aim to respond within 24 hours.

  • Tumakuru (Tumkur), Kunigal, Tiptur and Sira
  • Kolar, Malur, Bangarapet and KGF
  • Chikkaballapura (Chikballapur), Chintamani, Gauribidanur and Sidlaghatta
  • Booking refunds, delay interest and incomplete layouts
Office: S Jain & Attorneys, 3rd Floor, Blue Cross Chambers, 306, B-Wing, Infantry Road, Bengaluru, Karnataka 560001. Phone +91 70195 04495

RERA lawyer for Tumakuru (Tumkur), Kolar and Chikkaballapura: new layouts in one district, disputes in two

If your plot, villa or flat in these districts is overdue, incomplete or not yet delivered, the Real Estate (Regulation and Development) Act, 2016 governs it just as it governs a Bengaluru project. Section 2(zn) counts "the development of land into plots" as a real estate project, and under Section 18 you may withdraw with a refund and interest, or continue with the purchase and be paid interest for every month of delay, once the promoter misses the possession date in your agreement. This is important in these districts because nearly everything registered is a layout: on 18 November 2026 the K-RERA register recorded 593 approved projects in Tumakuru, Kolar and Chikkaballapura, and 549 of them were plotted developments. Wherever the project is, the complaint goes to one Authority in Bengaluru, and our article on running a K-RERA complaint from outside Bengaluru sets out how to do it from your district.

Tumakuru's register has grown far faster than its disputes. Only 6 Tumakuru projects were registered in 2018 to 2020. In 2023 to 2025 there were 135, and 69 more in 2026 up to 18 November. All 174 registered since January 2025 are layouts of plots, 156 of them in Tumakuru taluk, and 149 of their pages name the Tumakuru Urban Development Authority as the approving authority. Just 3 final K-RERA orders concern Tumakuru projects, all on apartment projects of one developer, and none on a layout. That is too little to reveal a pattern, and most of the register is recent: in the twelve months after 18 November 2026, 41 Tumakuru projects reach their completion dates. If work on yours has halted before then, see complaining while the possession date is months away.

Kolar and Chikkaballapura have a dispute history by now. Counted by each order's project, K-RERA has issued 35 final orders on Kolar projects, 25 of them on projects the register places in Malur taluk, and at least 39 on Chikkaballapura projects, every one a plotted layout. For every 100 registered projects that is about 18 orders in Kolar and at least 23 in Chikkaballapura, compared with about 189 in Bengaluru Urban counted the same way, and about one in Tumakuru. The Kolar orders return again and again to money paid at booking. In Chikkaballapura they cluster on a few layouts sold years ago, and two of them, in Gauribidanur and Sidlaghatta taluks, account for 23. Our article on what a developer may take before the agreement is registered sets out the ten per cent ceiling that applies at that point.

Tumakuru, Kolar and Chikkaballapura on the K-RERA register

174

Tumakuru layouts registered since January 2025

Every one a plotted development, 156 of them in Tumakuru taluk, with 7,633 plots between them. The district registered 6 projects in 2018 to 2020 and 135 in 2023 to 2025.

63

Newer Tumakuru projects past their completion date yet listed as ongoing or new

Of the 208 registered since November 2021, 77 had gone past the completion date on the register by 18 November 2026, even after adding the four months of K-RERA's order of 10 August 2026 where it applies, with no extension recorded. The pages of 63 still described them as ongoing or a new launch.

35

Final K-RERA orders on Kolar projects

On 14 projects. 25 of the orders are on 10 projects the register places in Malur taluk, and one mixed development there accounts for 9. Read with the orders, 14 seek the return of a booking amount or an advance, on 7 projects.

39

Final K-RERA orders on Chikkaballapura projects

All on plotted layouts, on 14 projects, and two layouts account for 23. A floor: 17 more orders list the Sidlaghatta layout under another name, so the matching method leaves them out.

Counted by S Jain & Attorneys from the public project register, project pages and order list on rera.karnataka.gov.in, read on 18 November 2026. Each order is matched to its project on the register by registration number or by exact project and promoter name, not by the district shown on the order list, so order counts are a floor. Completion dates include the four months that K-RERA's order of 10 August 2026 added where a project's completion date fell on or after 28 February 2026. Relief counts come from what each buyer stated, read with the orders. The register changes daily.

What the orders from these districts turn on

Six situations from the Kolar, Chikkaballapura and Tumakuru records

Each answer starts from the Real Estate (Regulation and Development) Act, 2016 and the K-RERA orders on projects in these districts. An order is one case on its own evidence, so treat it as a pointer to what must be proved, not to the result in yours.

Pulled out after paying a booking amount, and the developer is holding on to it?

Section 13(1) bars a promoter from accepting more than ten per cent of the cost of a plot or apartment as an advance or application fee before a written agreement for sale is entered into and registered, and Section 11(5) allows it to cancel an allotment only in terms of the agreement for sale. Getting a booking amount or an advance back is what 14 of the 35 Kolar orders, on 7 projects, were about, and several Malur complaints closed after the developer repaid it. Where the buyer withdrew of their own accord, an August 2023 order allowed the deduction the booking form provided for, without interest, while a June 2026 full bench order refused a "non-refundable" forfeiture because no loss was shown and directed a full refund, again without interest. See when the developer forfeits a booking amount.

Paid a marketing firm or an agent instead of the developer?

Where one company develops a layout and another sells its plots, the Explanation to Section 2(zk) deems both of them promoters, jointly liable. Section 4(2)(j) has the promoter disclose its real estate agents for the project, and of the 411 project pages for these districts registered since November 2021, 396 disclose none. In an October 2026 Malur order the developer argued that money paid through an agent did not reach it, and in a June 2026 order the claim against the marketing company failed because it had no contract with the buyer. Our note on a developer who denies receiving booking money goes through that defence.

Bought the plot under one contract and the villa or layout works under another?

A real estate project takes in "the development works" on the land (Section 2(zn)). On one Malur villa project, K-RERA held the construction company to be a promoter alongside the developer that sold the plots, treated the site sale and the construction agreement as parts of one project, and in orders of May and November 2026 directed the villa to be finished, with delay interest at the Rule 16 rate from the contractual possession date. On a Sidlaghatta layout, a March 2023 order directed the roads, drainage, electricity and water supply a buyer had paid for under a separate development agreement. Settle which agreement fixes your date before anything else: the delay-interest arithmetic.

Your plot number is not in the sanctioned layout?

Section 3(1) prohibits booking or sale of any plot in a planning area before the project is registered, and the application must carry the sanctioned layout plan (Section 4(2)(d)). In an October 2025 Malur order, 15 plots paid for in full in 2018 lay outside the sanctioned portion of the layout, and the full bench dismissed the refund complaint as not maintainable, leaving the buyer to the civil court. Each project page tabulates its plots by number and size, so look for yours there before paying. Our note on confirming a project's K-RERA registration points to the right fields.

Partly refunded, with the balance due in instalments?

Rule 17 of the Karnataka Rules makes a refund with interest payable within sixty days of falling due, so an instalment plan is a concession you choose to give. On one Gauribidanur layout, buyers settled in March 2022, December 2022 and February 2025 for 5 or 6 instalments, one a month, and some afterwards told the Authority that instalments were missed. In September 2023 K-RERA ordered the outstanding balance under one such joint memo to be paid within 60 days, and a September 2026 Chikkaballapura taluk order directed the balance outstanding, with interest from November 2019. Before you settle, see what you can lose by settling on the developer's terms.

Your new Tumakuru layout is past its registered completion date?

The register carries the completion date the promoter declared when it registered (Section 4(2)(l)(C)), and only the Authority extends a registration, under Section 6 or by keeping it in force under Section 7(3). Its order of 10 August 2026 extended by four months the registration and corresponding completion timeline of every registered project whose original, revised or extended completion date falls on or after 28 February 2026, except projects registered on or after 1 August 2026. Even so, 77 of the 208 Tumakuru projects registered since November 2021 had gone past their date by 18 November 2026, none with an extension recorded on the register. A date gone by is the moment to study the quarterly updates and put questions to the developer in writing. What it means for your own claim depends on your agreement for sale: see refund or interest once the developer is overdue.

How a complaint from these districts moves

Plot, payments, settlement, collection

The sequence is the one every K-RERA complaint follows. What differs in these districts is where it tends to go wrong: the plot is not where the buyer thought, the payments are not all documented, or a settlement goes in without terms that bite.

  1. 1

    Locate the plot on the project page

    Days 1-7

    A registered layout's K-RERA page tabulates its plots by number and size, the approved plan, the timetable for roads, water supply, sewage and electricity, the project bank accounts and whether the land is held under a joint development agreement. We match your plot number, agreement and receipts to that page at the outset, because a plot outside the sanctioned layout can fall outside the Authority's reach.

  2. 2

    Rebuild the payment history

    Days 7-15

    Who was paid, when, by what mode, and what the developer has since repaid. In a September 2026 Chikkaballapura order the principal was fixed from the payment statement at less than the buyer's figure, and interest ran on the unrecovered balance. In a November 2026 Malur villa order the buyers' own interest calculation was not accepted because it did not match their two agreements.

  3. 3

    Weigh any settlement against the Act

    Several months

    Of the 42 Kolar and Chikkaballapura orders we read, 18 closed on a settlement, a payment during the proceedings or a withdrawn complaint, and 3 were dismissed because the buyer ceased attending. A settlement can be a sound result. Before agreeing to one, compare it with what Section 18 and Rule 16 interest would yield, and see that the memo states what happens if a payment is missed.

  4. 4

    Make the order pay

    From the outset

    Interest or compensation left outstanding is recoverable as arrears of land revenue under Section 40(1). Study the order the day you receive it: in one Malur case the order of May 2026 named another layout and other sums, and it was corrected under Section 39 in June 2026 after the buyers wrote in. Our article on collection through the Deputy Commissioner takes it from there.

How long each stage takes depends on the Bengaluru benches' lists and on whether the developer turns up at all. Several of the orders we read were passed with the developer absent.

Before you pay for a plot in a new Tumakuru layout

Tumakuru's new layouts are small and quick. The 174 registered since January 2025 have a median of 25 plots each and a median of about 19 months between registration and their declared completion date. So study the project page before you pay anything, not after the date has gone by. Confirm that the project was registered before any booking was taken, since Section 3(1) rules out booking or sale until then, that your plot number appears in the page's plot table, and what its civil works timetable commits to for roads, water and electricity. Pay only into the project bank account the page displays: every one of the 411 project pages we read for these districts carries the Authority's own notice telling buyers to deposit money in the approved account only.

Then watch the page. Rule 15(1)(D) of the Karnataka Real Estate (Regulation and Development) Rules, 2017 has the promoter upload, within fifteen days after each quarter ends, the bookings made, the status of the internal infrastructure with photographs and the status of approvals, and a K-RERA circular of July 2026 fixes a penalty of Rs 25,000 for each update filed late or not at all in 2026-27. Where the land is held under a joint development agreement, as 38 of the 208 newer Tumakuru project pages declare, see what happens when the developer defaults on a joint development. If the developer is in insolvency proceedings, or a consumer case fits your purchase more closely, the Bengaluru RERA page compares the forums.

Share the booking form and the payment proofs

With the booking form or agreement, the receipts and bank entries and the project's K-RERA registration number we can form an initial opinion: whether a refund, interest for the delay or completion of the layout is the stronger claim, and what any proposed settlement would surrender.

Every enquiry is privileged and confidential. Nothing you share leaves this firm.

Frequently Asked Questions

Does K-RERA deal with a layout plot in Tumakuru, Kolar or Chikkaballapura?+

Yes. The Real Estate (Regulation and Development) Act, 2016 counts the development of land into plots for sale as a real estate project, and Section 3(1) prohibits booking or sale of plots in a planning area before the project is registered with the Karnataka Real Estate Regulatory Authority, which takes complaints from every district of the State. On 18 November 2026 its register recorded 593 approved projects in these three districts, and 549 of them were plotted developments.

I withdrew from a plot booking and the developer is holding the booking amount. Can K-RERA order it returned?+

It can, but the result depends on the booking form and on who was at fault. Section 13(1) of the Act bars a promoter from accepting more than ten per cent of the cost of a plot or apartment as an advance or application fee before a written agreement for sale is entered into and registered, and Section 11(5) allows a promoter to cancel an allotment only in terms of the agreement for sale. Of the 35 final K-RERA orders on Kolar projects, 14, on 7 projects, seek the return of a booking amount or an advance, and several Malur complaints closed after the developer repaid. Where the buyer withdrew of their own accord, an August 2023 order allowed the deduction the booking form provided for, without interest. A June 2026 full bench order refused to enforce a non-refundable clause because the developer showed no loss, and directed the whole booking amount refunded, but without interest, as the cancellation arose from the buyers' own failure to keep to the payment schedule.

My plot number is not in the sanctioned layout plan. Can I approach K-RERA at all?+

Possibly not. In a Malur order of October 2025, a buyer had paid in full in 2018 for 15 plots that fell outside the sanctioned portion of the layout, and the K-RERA full bench dismissed the refund complaint as not maintainable because those plots were outside the registered project. The buyer remains free to approach the civil court. A registered project's page on rera.karnataka.gov.in tabulates its plots by number and size, so confirm that your plot appears there before you pay.

I bought a villa plot and took a separate construction agreement. Who is liable for the delay?+

Where one company sells the plots and another builds on them, the Explanation to Section 2(zk) of the Act deems both of them promoters, jointly liable. On a Malur villa project, K-RERA treated the site sale and the construction agreement as parts of one project. Its May 2026 order directed the construction company to finish the villa and pay delay interest at the Rule 16 rate from the contractual possession date, and its November 2026 order gave the same directions against the developer, which had signed both agreements with those buyers. Settle which agreement fixes the possession date before you lodge the complaint.

The developer settled for a refund in instalments and the instalments have dried up. What now?+

Write to the Authority with the joint memo and a bank statement showing what arrived and what did not. In a September 2023 Gauribidanur order, where the developer had missed instalments set out in a joint memo, K-RERA directed the outstanding balance to be paid within 60 days. Interest or compensation left outstanding under an order is recoverable as arrears of land revenue under Section 40(1) of the Act. Rule 17 of the Karnataka Rules makes a refund with interest payable within sixty days of falling due, which any instalment plan should be weighed against before you accept it.

RERA help across Karnataka

Is your project in another district?

Every K-RERA complaint, wherever the project is, goes to the same Authority, which sits in Bengaluru. What differs from district to district is the kind of project and the kind of dispute. These pages set out what the project register and the orders show for each.

Homebuyer & Real Estate Guides

53 guides on RERA & Homebuyer Disputes, each written for the reader who has the problem, with the statute, the forum and the timelines set out.

Property & Real Estate Law

I Live Outside Bengaluru and My Builder Has Not Delivered: Can I File and Run a K-RERA Complaint Without Travelling Again and Again?

Property & Real Estate Law

My Builder Has Defaulted on the Joint Development: What Can I Do Under RERA, and Am I Liable to His Buyers?

Property & Real Estate Law

My Agreement for Sale Has an Arbitration Clause: Can the Builder Force Arbitration Instead of K-RERA?

Property & Real Estate Law

We Are 59 Buyers and the Builder Says the Project Has 966 Allottees: How the 100 or 10 Percent Threshold Is Really Counted

Property & Real Estate Law

The Builder Says It Never Got the Booking Money I Paid on Its Sales Manager's Instructions: Must I Pay Again?

Property & Real Estate Law

I Filed a K-RERA Complaint and the Builder Has Sent an Arbitration Notice Under Our Agreement: Must I Go to Arbitration?

Property & Real Estate Law

I Paid a House Building Co-operative Society for a Site Years Ago and It Has No Land: Can I Go to K-RERA or Must I Go Elsewhere?

Property & Real Estate Law

I Paid a Welfare Society for a Plot in Its New Layout and Got Nothing: Can K-RERA Order the Society to Refund Me?

Property & Real Estate Law

Work on My Project Has Stopped but the Possession Date Is Still Months Away: Can I Complain to K-RERA Now?

Property & Real Estate Law

My Father Booked the Flat and Died Before Possession: Can We Continue His K-RERA Complaint and Take the Flat as His Heirs?

Property & Real Estate Law

The Occupancy Certificate for Our Villa Has Been Cancelled After We Moved In: What Happens to Us Now?

Property & Real Estate Law

I Have Finished Building My House in Bengaluru but Have No OC and BESCOM Refuses Power: What Can I Do?

All 53 guides on RERA & Homebuyer Disputes
View all legal insights →

About this page

Reviewed by Advocate Sharan Jain, founder of S Jain & Attorneys, Bengaluru, practising before the Karnataka High Court, K-RERA, the Karnataka Real Estate Appellate Tribunal and the consumer commissions, and a panel advocate to KUIDFC (a Government of Karnataka undertaking). He is also pro bono counsel for the High Court Legal Services Committee and a State Executive Committee Member of INTUC Karnataka.

This page is general legal information, not legal advice, and reading it does not create an advocate-client relationship. The figures are counts from public records on the date stated, not indications of outcome. In line with the Bar Council of India rules, this website does not advertise or solicit work. The information here is provided only for visitors who seek it.